Northwest Precision Manufacturer
50% reduction on critical asset process
"Westbury didn't just identify the problems — they embedded with our team and drove the change from the inside."
The challenge
A precision engineering firm was failing OTD due to long lead times and inconsistent changeovers. Production bottlenecks were costing an estimated 160 hours per year in lost capacity.
Our approach
We deployed a Lean transformation programme — mapping the full process & identifying 3 critical areas, asset capability, standard work and total productive maintenance. By combining all 3 areas to improve on, changeovers were quicker and standard throughout operations, critical parts repaired and spares shelved. Finally empowering ownership to the operators to perform daily TPM's for safety and performance.
Outcomes
- 50% reduction in changeovers
- Change over time from 70 to 35 minutes
- £202k capacity valued recovered
- Team trained in TPM & standard work principles for self-sustaining improvement